Monday, March 10, 2025

Week 6 Update

Client Feedback & Priorities:

  • Client is pleased with recent UI improvements
  • However we anticipated that we are still expected to meet performance targets consistently.
  • Team proposed focusing more on backend optimization to balance performance and UI stability. 
  • Client agreed and reminded us of backlog requests made last semester and should follow up on that, especially:
    • Admin feature enhancements.
    • Student application progress saving ("save and resume" functionality).

Next Steps:

  • Prioritize backend tasks to meet performance thresholds.
  • Start scoping "save and resume" feature (critical for user experience).
  • Review client’s backlog to align sprint goals with their long-term requests.

See simplified product velocity chart below: